Benefits From Super Irrigation Projects

What benefits do farmers in the West benefit from "SUPER IRRIGATION CONSTRUCTION"
 
The reason it is called "super irrigation sewer" is because the irrigation sewers of this project are very "huge" in scale.
 
Specifically, Cai Lon sluice has 11 valves and locks 15m wide, each valve is 40m wide and weighs 203 tons. Cai Be sluice also has two 35m wide valve gates and a boat lock. Xeo Ro culvert has a width of 31.5m combined with a boat lock. Phase 1 of the project has an investment capital of 3,300 billion VND.
 
The leader of Irrigation Investment and Construction Management Board 10 (investor) said that according to the normal schedule, it would take at least 36 months to complete the Cai Lon and Cai Be sluice gates, but due to speeding up progress, two The sewer can be basically completed from the 17th month.
 
Currently, the Cai Lon sluice can be temporarily operated to serve production by the end of June, but the Cai Be sluice has been temporarily operated since February 2021 (progress beyond one dry season).