Irrigation Projects

Bao Chau Project

Bao Chau Culvert Lifting Machine
Bao Chau sluice gate is built to prevent salinity, maintain fresh water, alleviate waterlogging, and alum discharge during the rainy season. Upon completion, the project is also responsible for supplying saltwater and draining wastewater for shrimp farming in the dry season. This project was supplied by Yen Linh Co., Ltd. and put into use in 2016.
 
 
Technical parameters
 
Main hydraulic cylinder: 320/180x9200mm-MT4
 
Pushing force: 120T/ cylinder
 
Lock hydraulic cylinder: 100/45x250mm-MP5
 
Hydraulic power unit:
 
- Oil tank capacity: 1920L
 
- Electric motor capacity: 30 kW
 
- Piston hydraulic pump
 
- Working pressure: 199 bar