Rao Trang 4 lifting machine

Rao Trang 4 Hydropower Plant was built with an installed capacity of 14 MW, annual electricity output of over 46 million kWh located on Rao Trang Stream in Phong Xuan commune, Phong Dien District by Rao Trang Hydropower Joint Stock Company. 4 as an investor
 
In August 2019, Yen Linh Hydraulics Co., Ltd. installed, tested, and calibrated the system.
 
Hydraulic system lifts and lowers the valve gate
 
Hydraulic cylinder: 340/180-6,200 mm
 
Lifting force 2x110 Tan
 
Design pressure: 200 bar
 
Door lifting pressure: 170 bar
 
2000 L hydraulic oil tank
 
Electric motor 22 kw - 1450 rpm
 
Hydraulic pump: 45 cc; 350 bar
 
Completely imported hydraulic equipment
 
 
 
Hydraulic system lifts and lowers the water intake door
 
Hydraulic cylinder: 200/100-2700 mm
 
Lifting force 30 Tan
 
Design pressure: 200 bar
 
Door lifting pressure: 130 bar
 
500 L hydraulic oil tank
 
Electric motor 5.5 kw – 1450 rpm
 
Hydraulic pump: 12 cc; 280 bars
 
Completely imported hydraulic equipment